NEW QUESTION # 10
In the bucket planning mode of the capacity scheduling table, what happens if the sum of the requirements of all operations exceeds the available capacity of the bucket?
- A. The operation CANNOT be dispatched.
- B. The operation is rescheduled in the planning direction.
- C. The operation is rescheduled backwards.
- D. The operation is rescheduled to an alternative work center.
Answer: B
NEW QUESTION # 11
In the context of the capacity scheduling table, how do you define a pacemaker work center?
- A. By assigning it to the bottleneck operation
- B. By assigning it to the first operation of a routing
- C. By assigning it to the production version
- D. By assigning it to the capacity scheduling table
Answer: C
NEW QUESTION # 12
How do you assign resources in a master recipe with operations and phases?
- A. You assign resources to the operations.
- B. You assign resources to the sub-operations.
- C. You assign resources to the phases.
- D. You assign resources to the header of the master recipe.
Answer: A
NEW QUESTION # 13
For a production version to be valid and consistent, what requirements must be fulfilled? Note: There are 3 correct answers to this question.
- A. The consistency check must be performed.
- B. The deletion flag must NOT be set for the bill of material (BOM) or the routing.
- C. The lot size range must be within the lot size range of the assigned routing.
- D. The assigned routing and bill of material (BOM) must be valid in the entire validity period.
- E. The assigned routing and bill of material (BOM) must have the same validity period.
Answer: A,C,D
NEW QUESTION # 14
What are some options for creating production orders without using trigger points?
Note: There are 2 correct answers to this question.
- A. In assembly production, a sales order triggers the creation of a production order
- B. In make-to-stock production, confirmation of yield for sub-assembly triggers the creation of a production order
- C. In assembly production, confirmation of scrap triggers the creation of a production order
- D. In make-to-stock production, you can manually create production orders
Answer: A,D
NEW QUESTION # 15
In which master data objects do you maintain data to determine the duration of an operation for production?
Note: There are 2 correct answers to this question.
- A. Material master
- B. Production version
- C. Routing
- D. Work center
Answer: C,D
NEW QUESTION # 16
What is a work center hierarchy?
- A. A group of alternative work centers for production, structured in hierarchy levels by priorities
- B. A group of work centers in a production line that is used in sequence for production
- C. A group of work centers in a parallel sequence that is used to split production quantities and work on them in parallel
- D. A group of alternative work centers providing a cumulative available capacity for production
Answer: D
NEW QUESTION # 17
How do you model a production line in repetitive manufacturing?
- A. As a routing
- B. As a resource network
- C. As an operation
- D. As a work center
Answer: D
NEW QUESTION # 18
What is the purpose of the pull list in material staging?
- A. To control the flow of material from the supplier to the central storage location
- B. To control the flow of material from the central storage location to the production storage location
- C. To control the flow of material from the production storage location to the central storage location
- D. To control the flow of material from the supplier to the production storage location
Answer: B
NEW QUESTION # 19
Which time elements does MRP consider in backward scheduling to determine the basic dates for components from dependent requirements? Note: There are 2 correct answers to this question.
- A. Total replenishment lead time
- B. Planned delivery time
- C. In-house production time
- D. Operation duration
Answer: B,C
NEW QUESTION # 20
How can you limit the validity of a bill of material (BOM)?
Note: There are 2 correct answers to this question.
- A. By material type
- B. By material status
- C. By change number
- D. By plant
Answer: A,D
NEW QUESTION # 21
What is a prerequisite for the consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?
- A. A sales order is created.
- B. A sales order is delivered.
- C. MRP creates a dependent requirement.
- D. MRP creates a planned order.
Answer: A
NEW QUESTION # 22
You want to set up a make-to-order planning scenario for a finished product. The bill of material contains two components: one should be procured for each sales order individually, and the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?
- A. Choose planning strategy 50 (Planning without final assembly) and select the corresponding Mixed MRP indicator
- B. Choose planning strategy 50 (Planning without final assembly) and select the corresponding Individual/Collective indicator
- C. Choose planning strategy 20 (Make-to-Order) and select the corresponding Individual/Collective indicator
- D. Choose planning strategy 20 (Make-to-Order) and select the corresponding Mixed MRP indicator
Answer: C
NEW QUESTION # 23
Which objects can you change with a change number?
Note: There are 2 correct answers to this question.
- A. Bill of material
- B. Production order
- C. Work center
- D. Routings
Answer: A,D
NEW QUESTION # 24
You want to verify that the properties of a component batch align with the required properties of the raw material intended for a specific process order. What function do you use to accomplish this?
- A. Batch information cockpit
- B. Batch number assignment
- C. Batch where-used list
- D. Batch determination
Answer: D
NEW QUESTION # 25
Which of the following elements does MRP take into account during net requirement calculation?
Note: There are 2 correct answers to this question.
- A. Planned orders (unfirmed)
- B. ATP quantities
- C. Production orders
- D. Planned orders (firmed)
Answer: C,D
NEW QUESTION # 26
What can you use standard heuristics in Advanced Planning (PP/DS) for?
- A. To set default values in production master data
- B. To solve planning problems for defined objects
- C. To automate material movements in material staging
- D. To optimize costs and times in production plans
Answer: B
NEW QUESTION # 27
You are a consultant on an SAP S/4HANA Cloud greenfield project.
Which of the following aspects should you focus on to achieve and maintain clean core data quality? Note: There are 2 correct answers to this question.
- A. Stability
- B. Accuracy
- C. Timeliness
- D. Efficiency
Answer: A,D
NEW QUESTION # 28
......